Talex Solutions
*

Rollouts

IT environments nowadays has to follow changing business needs, software and systems upgrades. The pressure to keep up with the business' expectations makes IT departments to change the way they work. For companies which are about to upgrade theirs hardware infrastructure, Talex has prepared rollout services.

Rollout

Mass deployment of IT hardware including pre-installation, logistics, installation at client's offices, as well as deinstallation and utilization.

Rollout – stages:

  1. audit of existing infrastructure, hardware stocktaking,– Talex prepares a complete report of auditing branches with detailed list of equipment to withdraw
  2. hardware completation – being a parter of main IT hardware producers Talex negiotiates best offers and buys the equipment
  3. configuring and installation – workstations and servers are preinstalled at Talex' Rollout Factory with accordance to client's specyfication
  4. implementation – at the agreed term the hardware is installed at final loactions. The process may be performend at weekends or outside working hours not to disturb any normal activity of the staff
  5. recycling– the withdrawn equipment and hardware are transported to Talex' Logistics Center where it is utilized and recycled where possible. The data stored on HDD is erased and destroyed permanently with degaussing or physical desctruction

Our infrastructure

Talex owns the Rollout Factory and Logistics Center which allow multiple (even hundreds) workstations and servers preparation in a limited time.

Due to preinstallation process the hardware may be installed at final location during a single day. It may be also run during a night or weekend, so that it doesn't interrupt normal working hours.

We have developed a dedicated software and special procedures that allow a real-time monitoring of the whole process. Project managers have up-to-date information and data from any local branch or office.

Selected rollouts:

Bank Zachodni WBK SA

Project

Complete hardware replacement in Banks' branches across the whole Poland to allow implementation of the new centralized IT system.

Terms

2001-2003
rollout has been run during 38 weekends

Scale

  • 430 branch offices
  • more than 10 000 pcs. of hardware installed
  • more than 20 000 pcs. of hardware disposed
ING Bank Šl±ski SA

Project

A rollout of IT infrastructure to implement a centralized CEDS (Common European Desktop Services) - desktop management system.

Terms

2005

Scale

  • 329 branches
  • more than 10 000 pcs. of installed and disposed hardware

Case Study

Download pdf pdf
Bank Millennium

Project

A mass rollout of computer hardware at all bank's branches during 2 months.

Terms

2005

Scale

  • 301 branches
  • more than 5 000 pcs. of installed and disposed hardware
Kredyt Bank SA

Project

Rollout of IT infrastructure in headquarters and branch offices.

Terms

2007-2008

Scale

  • 20 headquarters offices
  • 80 branches
  • 280 branch offices
  • more than 5 000 pcs. of installed and disposed hardware
Ministry of Education

Project

The project co-financed by EU was targeted at the polish primary schools. The main aim was to create multimedia centers in Polish schools. Talex has implemented hardware at the schools' libraries of Greater Poland and Pomerania provinces.

Terms

2007 (54 days)

Scale

  • 841 schools' libraries
  • more than 3000 pcs. of installed hardware (workstations, servers, printing devices, LAN components)
  • 54 service teams
  • EU procedures

Project 2

Implementation of IT hardware at the 878 school labs of 4 provinces of Poland.

Terms

2007 (60 days)

Scale

  • 878 school IT labs
  • more than 5000 pcs. of installed hardware (desktops, servers, printing devices, LAN cabling)
  • 62 service teams
  • EU procedures